Daily Events on 2008/08/23 (Sat)

last updated at  2008/08/23 10:39:22 JST


<< prev day

@

next day >>


Station

Pass No.
20080823-

Contact time (UT)

Max. Elev.
 (deg)

Events

AOS

LOS

USC34

0100

07:41:03

07:52:42

16.6

OP/OG upload
XRT: TI-CMD
EIS: TI-CMD
SOT: TI-CMD
DR playback (by OP)

USC34

0200

09:17:15

09:29:56

37.5

OP/OG upload, XRT:TI-CMD, SOT:TI-CMD, EIS:TI-CMD (backup)
AOCS: Upload pointing table
DR playback (by OP)

SNT1

4000

10:07:12

10:20:58

82.6

SOT: Table Upload
XRT: Table Upload
EIS: Table Upload

USC20

0400

21:18:58

21:32:42

78.1

DR playback (by OP)

USC20

0500

22:58:52

23:06:03

7.9

DR playback (by OP)

Flare list(LM) : http://www.lmsal.com/solarsoft/last_events/


DR information

Remaining amount
(prediction)

- Mbits @ OP_START ( )


SOT

XRT

EIS

DR allocation [%]

70

15

15

DR allocation [Mbits]

-

-

-

DR TLMLMT [Mbits]

-

-

-


daily note

Note: 2day OP, next OP upload is scheduled on 25 Aug, Mon.

EIS table upload moved from pass 2 to pass 3, to better accomodate La Palma joint observations.

EIS:
- Support for HOP74.

- Will adjust slit focus in weekend plan. Pre/Post-adjustment verification observations require at least 475Mb of data allocation (preferably 600Mb), and at least 16 hours of pointing control (preferably a whole day).

 Plan:    1. Disk center tracking for 3 1/4 hours
          2. Off-limb fixed pointing for 3 1/4 hours
          3. Disk center tracking again for 1 1/4 - 5 hours
          4. Focus adjustment
          5. Repeat steps 1-3.



SOT: Support for HOP74

XRT: QS observations.


CHIEF
TOHBAN

SUB
TOHBAN

CP

SOT CO

XRT CO

EIS CO

EVENING

Sugita

Sterling

Okamoto/Fujimura

Narukage

Brooks

MORNING


operation files

pointing file : none