Daily Events on 2018/08/21 (Tue)

last updated at  2018/08/21 14:51:23 JST


<< prev day

@

next day >>


Station

Pass No.
20180821-

Contact time (UT)

Max. Elev.
 (deg)

Events

AOS

LOS

MSP1

8010

07:37:16

07:50:46

46.5

MDP: MDP diag (DCBC-410)
MDP: MDP reboot (DCBC-410)
MDP: MDP/SPT patch (DCBC-410)
XRT: CCD Bakeout Heater is ON

USC20

0200

08:43:09

08:56:10

75.4

MDP: MDP diag (DCBC-410)
MDP: MDP reboot (DCBC-410)
MDP: MDP/SPT patch (DCBC-410)
DR playback (by Real command)
XRT: CCD Bakeout Heater is ON

SNT1

4010

09:33:43

09:46:41

30.1

OP/OG upload

PRT1

2000

10:05:09

10:18:31

43.2

OP/OG upload (backup)
AOCS: Upload pointing table
SOT: Recovery
XRT: CCD Bakeout Heater is ON

USC20

0400

20:44:20

20:57:11

26.2

XRT: CCD Bakeout Heater is ON

USC20

0500

22:22:10

22:34:04

23.3

XRT: CCD Bakeout Heater is ON

Flare list(LM) : http://www.lmsal.com/solarsoft/last_events/


DR information

Remaining amount
(prediction)

- Mbits @ OP_START ( )


SOT

XRT

EIS

DR allocation [%]

54

23

23

DR allocation [Mbits]

-

-

-

DR TLMLMT [Mbits]

-

-

-


daily note

****************************************************************************
- All scientific observations are canceled, because of the MDP 2-bits error.
- MDP recovery  
****************************************************************************



-----------------------------------------------------------------------------------------------
Typhoon No19 is approaching the Uchinoura area. Since there is a possibility that the USC contact may be canceled, SNT1 has beem added as a backup.
As a USC contact can be used, CO should carry out planning as usual.
-----------------------------------------------------------------------------------------------

Co-alignment program run:

Please run co-alignment program during the period for the three instruments.
- If the solar condition is not permitted, please delay to the next timeline.
- The sequence should start exactly 15 minutes after the pointing change to stabilize the satellite pointing drift.
- 2 hours for N-limb at *** 930*** arcsec and 2 hours for E limb at *** -970*** arcsec.
- Not necessary to be during SAA-free time.
- For XRT, take G-band data every 5 minutes instead of 8 minutes. This is just for the N limb run. 8 minutes cadence is still OK for the E limb run.
- For XRT, please take data even during SAA and twilight periods.
- For SOT, please use CTM HYSTERISIS (not CT RUN) at the start of each SP program
- For EIS, please run Imada's new co-alignment program

[Maintenance Note (manabe)]
The web servers will be switched.
As a result, the update of the external web server stops for the following period.
8/14 00:00 - 8/21 10:00 (JST)
To see the latest information, refer to the internal web server from the CP, CO machine.
For viewing from the outside, please use port forwarding etc and refer to internal server.

XRT:
- CCD bakeout ends 6UT on 08/22
- Post bakeout run
- AR obs.
- HOP 349
- Co-alignment program
- IHOP 362

SOT:
- AR obs
- Co-alignment program
- QS obs.
- IHOP 362

EIS:
- AR obs.
- QS obs.
- Co-alignment program
- IHOP 362

[Maintenance Note (Yamagishi), for CO/CP/RT Tohban]
Some software packages will be updated and security patch will be installed on machines
'cpws', 'xrtco', 'eisco', 'sotcows1', 'sotcows2', 'aocswin', 'higashirinkan', and 'ope-gw'
at 15:00-17:30(JST) on 21st August. When that's over, these machines will be rebooted.
Please do not use these machines during updating, and report if you have any trouble.


CHIEF
TOHBAN

SUB
TOHBAN

CP

SOT CO

XRT CO

EIS CO

EVENING

Yasuda

Matsumoto

Ishiguro

Matsumoto

Imada / Kawai

MORNING


operation files

pointing file : none